While during Material Creation/Change we want to Create/Update respectively both case for Valuation Accounting/Costing data .But We are unable to Activate Change Request . Error Message come like this .
Cannot update valuation data for TEST-ALL-DATA/XXXX; plant set up for material ledger....
Case-1 In our case Material Ledger is Active at Plant Level .
Comment : We don't want to deactivate this is our requirement.
Case -2: We Don't want to go MM01/MM02 to Create/Change Valuation Accounting/Costing Data.
Comment : We want to do this activity with in MDG-M
Case-3 We already know Snote: 1806108 there Point No : 21.
Our requirement is that we have to create/change Valuation accounting/costing data with in MDG.
So plz help us how to achieve this if Material ledger is Active at plant level.