Hi expert
now,We describe an scenario about MDG-M.
that are:
・MDG server import material data as XML file using Master Data Import in MDG.
・MDG server(ERP) has already have the material data (same matnr code) in active area.
・I want to import the Data and change on MDG in such a way as to create new change request.
but when we imported the xml file using Master Data Import, the system said
"Material FERT0214(matnr) exist with outstanding change request 283; Material rejected"
(Message no. MDG_MAT_LOADER_MSG012)
Can we resolve the problem?
If yes, Please teach me.
Best regards